Early spring progress!

As winter turned into spring, we made progress on your new school! We are putting in the new turn lane and entry drives on 21st Ave. We will be pouring the offsite concrete curbs, sidewalks, and entry drives, and completing the offsite asphalt paving. We are also pouring the onsite curbs to prepare for onsite paving and concrete hardscape.

Inside the buildings, we have millwork, tile, and ceiling grid being installed in Building 300 (classroom). We have paint beginning in Building 100 (admin). Building 400 framing and wall electrical/plumbing/mechanical is nearly complete and will be ready for drywall shortly. Bl 200 framing has just begun and rough electrical, plumbing, mechanical is also in progress.