It’s coming together!

Despite the challenges of the last few months, we’ve been making great progress on your new school!

OUTSIDE: Irrigation is being installed and grass just a few weeks away. The landscaper is also installing decomposed granite around the perimeter of the ball field and will continue throughout the campus. The chain link fencing at the ball fields is complete and the fencing contractor will start wrought iron at the end of the week. Playground installation is almost done and will be followed by play sand, wood chips and rubber surfacing.

INSIDE: Air conditioning will begin on Wednesday in Building 300 and upon building acclimatization, flooring will be installed. After Building 300, A/C will be turned on in Building 100 then 400 and 200. Tile has begun in Building 200 and kitchen equipment will soon follow. Paint is nearly complete in Building 200 as well, and all trim finishes will start once paint is complete.