We have begun hanging drywall in Building 300 and will be hanging drywall in Building 100 on Monday, 2/24/2020. We have installed the acoustic deck on the gymnasium (Building 200). Wall framing has begun on the second floor of Building 400, and the first floor slab is scheduled to pour at the end of next week.

As part of our QA/QC process, we take 360 degree photos of each room before we hang drywall. This is helpful in the future because it allows the end user to locate water lines, shut-off valves, fan coils, wall backing, etc. without having to open the walls or ceilings.

Today, we’re sharing some of those 360 photos with you! Check them out below!